
January 1997
No. 3
Siting Issues for
Wind Power Plants
|
|
ike any other major energy project, a wind
power plant must go through a siting review process to acquire the permits and approvals
needed to allow construction and operation to proceed. The basic goal of this process --
which can occur in a variety of federal, state and local jurisdictions -- is to ensure
that the plant will be safe, environmentally sound and make appropriate use of land. This
report reviews issues arising in the siting of wind power plants and describes some of the
key elements of a sensible siting review process.Background
Siting power plants and transmission lines used to be a
relatively straightforward process. A utility submitted to the appropriate agency a
request describing the presumed need for the facility and its claimed benefits for utility
customers. The agency, after reviewing the documents and conducting a hearing, usually
granted the request. While there was sometimes public opposition to this process, it was
rarely effective in stopping projects. |
|
| Siting such facilities today is
far more difficult because governments have become more sensitive to the potential effect
of projects on the environment and nearby communities. The regulations and laws governing
siting have become more complex, state and federal siting agencies are not as likely to
approve power company projects without extensive review, and various interest groups have
become more effectively involved in siting proceedings. Large wind energy projects raise many of the same siting issues as other
energy projects. For example, there may be concern about truck traffic during construction
and operation, the health effects of electromagnetic fields caused by transmission lines,
and social justice and equity issues. (An example of the last might be a proposal to build
a plant in a low-income area or an area of religious or cultural value to Native
Americans.) In addition, wind projects present some unique siting challenges that require
special consideration, including the following:
- Visual and noise impacts in scenic areas or near
residential communities. Wind turbines are highly visible structures that often are
located in conspicuous settings, such as ridges and hillsides. They also generate noise
that can be disturbing to nearby residents. These problems often can be mitigated through
sensitive design practice (such as tubular towers), appropriate setbacks, noise abatement
and other measures.
|
Wind energy projects are
subject to the same laws and regulations that govern siting of other power plants. |
- Potential impacts on birds and other wildlife. In
some locations, wind turbines and associated electrical equipment have killed or injured
birds such as hawks and eagles. Pre- and post-construction studies may be needed to
measure wildlife impacts and devise strategies for mitigating or offsetting them, and some
locations may be ruled off-limits to wind development. Soil erosion is another potential
problem that may be raised in the siting process.

- Land owners' rights. Wind power plants often pay
substantial rents and royalties for the use of land. This can be a boon to land owners,
but also may raise concerns about whether their rights are being sufficiently protected.
For example, a wind turbine on one person's land may interfere with the ability of a
neighboring land owner to develop a wind project. Land owners also may be concerned about
fair compensation for use of land.

- Staged development. Unlike most conventional power
projects, wind plants can be built in multiple stages, so that a 25 megawatt (MW) plant
today can grow to 500 MW in the future. This characteristic can complicate siting
proceedings, since the economic feasibility of the first increment may depend upon the
developer's ability to build the rest.
It is in both the developer's and the public's interest
that the siting process address all legitimate issues in an open, fair and unbiased
fashion, while minimizing costs for the participants and delays in reaching a decision. In
some cases, the result of the process may be to rule out a proposed site for wind
development. In other cases, it may be determined either that the issues raised are not of
serious concern, or that specific measures can be taken to address them.
Who is involved?
Many different groups and individuals may be involved in
the siting of a wind power project. One key to developing a sensible siting process is to
understand the differing roles, interests and priorities of the various stakeholders. The
major participants usually include the following.
- The wind developer. The wind project
developer, typically an independent power company or a utility, usually initiates the
siting review process by submitting a request for a permit to the appropriate agency. The
developer's immediate interest in the process is clear: to win approval for the project as
quickly and as cheaply as possible. Long, expensive proceedings with an uncertain outcome
wreak havoc on a developer's ability to secure financing. Beyond the success of any one
project, the developer wants to demonstrate a successful project record to maintain its
credibility with investors, policy makers and the general public.

State government. Most siting process
activity occurs at the state and local levels. At the state level, siting boards, land
commissions, environmental quality boards or similar bodies often have the authority to
grant construction and operating permits for power projects that are above a certain size.
In some states, the state public utility commission or siting board must grant a
certificate of need to permit a power project to be built. If a transmission line is
needed, that also can trigger state involvement. Often, an environmental impact assessment
will be required. This can be a formal process in itself, requiring an analysis of
environmental impacts, an often detailed comparison of alternatives to the proposed
project, and opportunities for public comment.

- Local government. County-level planning and
zoning boards often are heavily involved in providing siting approval. Wind developers
usually must demonstrate compliance with applicable land use designations and zoning
ordinances. As with most state-level proceedings, several hearings may be required; these
hearings may involve an administrative judge, lawyers, rules of discovery and other
legalities.

- Federal agencies. If a wind project is planned
on federal land, then the agency owning or managing the land (such as the Bureau of Land
Management or Forest Service) probably will be involved in siting approval. Even on state
or privately owned land, federal agencies may participate in some fashion. For example,
the U.S. Fish and Wildlife Service may want to consider whether a project poses an
unacceptable hazard to birds or other wildlife under its protection. Federal agencies also
can provide advice, comments or testimony in state- and local-level proceedings.

- Community groups and activists. Community
groups and activists also frequently participate in siting processes to ensure their
concerns are heard. Their views can carry considerable weight with state and local
officials. Some groups may support wind projects because of the jobs and tax revenues
generated, while others may be skeptical because of concerns about wind turbine noise,
visual impacts, traffic disturbance during construction and other issues. Local land
owners may play an especially important role, since wind plants can pay substantial
royalties for land and wind rights and, therefore, affect property values.

- Environmental organizations and activists. Like
community groups, environmental organizations and activists can greatly influence siting
processes. A wide diversity exists in the kinds of groups and the issues that concern
them. Local groups often are concerned about issues such as soil erosion, conflicts with
birds, and impacts on scenic or environmentally sensitive areas. Regional and national
organizations also may focus on such issues, or they may stress wind power's benefits to
air pollution and global warming. Community and environmental organizations and developers
sometimes challenge siting processes or decisions in the courts if they believe laws and
procedures were not properly followed.

- The general public. The general public
sometimes is perceived to be a passive observer of the siting process, but this viewpoint
underestimates the role public opinion can have in swaying the views and actions of the
central participants. Ultimately, wind power can succeed only if it wins public support
both in the abstract, as an alternative to polluting fossil fuels, and as a technology
that can be sited and built responsibly and effectively.
Guidelines for wind facility siting
Siting a wind power project involves negotiation between
the various participants to determine whether a project will be allowed to proceed and, if
so, under what conditions. This negotiation often focuses on striking a balance between
competing issues and concerns, such as social equity and the environment. Federal agencies
and state and local governments have powerful roles to play in determining the goals,
schedule, procedures and decision criteria that govern the siting process. While the
details of siting processes will vary widely, several general guidelines can be suggested: |
The siting process should
address all legitimate issues in an open, fair and unbiased fashion, yet minimize
participant costs and delays in reaching a decision. |
- Significant public involvement. A critical
feature of a sound siting process is that it provide opportunities for significant and
early public involvement. The public has a right to have its interests considered in
siting major power plants; without public involvement, a much greater likelihood exists
for later opposition and costly litigation. Public involvement provides an opportunity for
affected groups and individuals to learn about the project and to express their concerns.
At a minimum, the public in particular any residents living near a proposed project
-- should be notified of a siting application, the siting agency should hold public
meetings and accept public comments, and the agency's draft and final decisions should be
made available for public review.

- Reasonable time frames. A legitimate concern
of wind developers is that an open siting process, in which a large number of issues are
raised, can result in long delays in reaching a final decision. One way to address this
concern is to establish reasonable time frames in which the application for siting is to
be reviewed, hearings held and a final decision reached. Deviations from this schedule
should be rare and justified only in special circumstances. The definition of a reasonable
schedule will depend upon the situation, but it must include adequate time for public
notification and preparation of comments by stakeholder groups.

- Clear decision criteria. An efficient and fair
siting process requires that the siting agency establish in advance the criteria to be
used in making its decisions. The agency should: (1 ) list all the factors to be
considered in the decision, (2) specify how the factors are to be weighed against one
another and (3) set minimum requirements to be met by the project. The factors for
consideration will depend upon the circumstances. A state siting board, for example, might
consider such factors as whether the project meets an identifiable need for power, the effects it will
have on the environment and land use, and whether it will put a significant burden on
local services and infrastructure. The final decision should consist of the best balance
among the criteria established by the board. This process inevitably will involve some
subjective judgment, but, in general, the more clarity in the decision criteria, the
better.

Coordinated siting process. Another way to
make the siting process more efficient is to allow developers to obtain all the permits
they need from one state agency -- or otherwise to coordinate the processes of different
agencies, such as those at the state and local levels -- to prevent duplication and delay.
It is important to recognize that state and local governments may have different but
complementary responsibilities. Consideration should be given to identifying the roles for
each agency in any particular siting area, their methods for exchanging information and
expertise, and how the agencies might be involved productively in different stages of the
siting review process.

- Expedited judicial review. It should be the
goal of any siting process to follow procedures and produce decisions that are acceptable
to the participants and, consequently, do not prompt a court challenge. Should a challenge
occur, however, it is important that the judicial review process proceed efficiently and
reach a decision in a reasonable amount of time. In designing a siting process with
expedited judicial review, some factors to consider include: defining who should have
legal standing, setting reasonable time frames in which a suit can be filed, setting clear
standards for review and specifying the award of costs. Ideally, any appeal of a court
decision should be made directly to the state's highest court.

- Advance site planning. In many cases it will
be useful for a siting agency to define in advance the general geographic areas that would
be acceptable for wind projects. This would not eliminate the need for a siting review
process, but it would help wind developers select sites and design projects that have the
maximum chance of success.
Wind siting considerations
States and communities that are interested in wind energy
should develop, in advance, laws, ordinances and regulations for siting wind projects. The
advantage of this planning for developers and the public is that many important questions
can be discussed and resolved without arguments over specific elements of a proposal. In
addition, the existence of rules and procedures will increase the confidence of developers
in being able to win approval of suitably designed projects, while reassuring other
stakeholders that wind projects will not be rushed through without full, fair and open
hearings. |
Siting a wind power project
involves negotiation between the various participants to determine if the project will be
allowed to proceed and under what conditions. |
One useful step is for
communities such as towns and counties to implement zoning amendments for wind plants. For
each type of zone, whether commercial, industrial or agricultural, standards could be set
in the following areas:
- Wind turbine size, including maximum rotor size,
minimum and maximum height, tower height and base.

- Installation and design, including tower, rotor and
electrical safety, utility notification, warning signs and tower access.

- Siting, including setbacks from plant boundaries and
neighboring facilities, aesthetic design (such as tubular or lattice towers) and
clearances from electrical lines.

- Nuisance concerns, such as noise regulations and
television or radio interference.

- Other regulations, including insurance, public access
to wind facilities, and repair, maintenance and decommissioning requirements.
Often, such regulations can be based on similar statutes
(regarding radio towers, for example). In addition, regulations developed by other
communities can serve as a guide for discussion among wind developers, community and
environmental groups, and state and local planners.
Another element of wind power siting that deserves special
mention is the kind of environmental impact study, mitigation and potential remediation
that should be required. In recent years, the effects of wind power projects on birds, in
particular, have attracted considerable publicity and controversy. Siting agencies should
discuss their concerns with wind power developers and establish some rules and procedures
before specific project proposals are considered.
The National Wind Coordinating Committee is preparing a
handbook that will help states and communities address wind siting issues and develop
appropriate wind siting review processes.
Conclusions
The successful siting of wind power projects is one of the
most critical challenges facing the wind industry today. Developers, state and local
planners, federal agencies, and community and environmental activists all are interested
in implementing an efficient and fair siting process. Although further discussion and
study are needed, some guidelines can be suggested for the development of such a process.
Following these guidelines cannot guarantee successful siting in all cases, but it can
significantly ease the barriers to wind energy development while assuring continued public
support for wind energy.
References
NWCC wind siting handbook.
Model State Certification and Siting Code for
Electric Transmission Facilities (Keystone, Colo.: Keystone Center, 1994).
Best Practice Guidelines for Wind Energy Development (London:
British Wind Energy Association, 1994). |
Rules and procedures for
siting wind projects assure success for both developers and stakeholders. |
|
|
National Wind Coordinating
Committee
The content and form of the papers in this series have been
reviewed and approved by the National Wind Coordinating Committee. Committee members
include representatives from investor-owned utilities, public utilities, state
legislatures, state utility commissions, state land commissions, consumer advocacy
offices, state energy offices and environmental organizations. The purpose of the National
Wind Coordinating Committee is to ensure the responsible use of wind power in the United
States. The committee identifies issues that affect the use of wind power, established
dialogue among key stakeholders and catalyzes appropriate activities. |
The
Wind Energy Series is a product of the National Wind Coordinating
Committee (NWCC). The NWCC is a collaborative endeavor that
includes representatives from electric utilities and support
organizations, state legislatures, state utility commissions,
consumer advocacy offices, wind equipment suppliers and
developers, green power marketers, environmental organizations,
and state and federal agencies.
Issue Brief No. 3 | NWCC
Publications |
|