Western Transmission Planning Principles
Draft Planning Principals
for review and discussion June
4, 2003
June 3-4, 2003
2 World Trade Center Bldg.,
Skybridge A
121 SW Salmon Street
Portland, Oregon 97204
Problem:
-
Capacity of and “best use” of
current transmission system
-
Expansion of system.
-
How get transmission planning
process to incorporate “value” of resource types
-
Institutional framework not
set up to incorporate value of resource types.
-
How get common metrics
considered that are not the traditionally metrics used – so lots of
resistance.
-
How get yard sticks for
externalities incorporated into the transmission planning process.
Best use – public good.
Different than saying value from private investor.
Explanation of first principle, recognize are
talking about transmission planning, different
components, then rest follows. With this first principle, this principle
underlies all principles following.
1. Transmission planning should be integrated
with resource planning
Call for “integrated planning”
2. Transmission grid planning should be done on
a broad regional basis. (put introduction: in
order to capture all physical and commercial impacts and interactions in the
interconnection.) need to define what mean by “grid” means highest levels.
3. Transmission
planning processes should be transparent and facilitate the input of all
stakeholders in the region. Transmission planning
should be based on an appropriate planning horizon and be proactive and
responsive to needs of market participants. (put
in goals: in order to ensure timely system adjustments, upgrades, and
expansion.
4. Transmission planning should consider on an
equal basis all types of resources available to meet planning goals and to
address system resource needs and problems. (i.e.
look at alternative scenarios)
5. Electric system plans
should be based on a life cycle least-cost standard including
external costs such as environmental, societal impacts...need
to deal with” least cost”.
6. How measuring cost elements. RETURN TO
THIS!!!!!Transmission plans should report on the
methods and calculations clear….. evaluate all is
based on evaluating all resources including demand-side and intermittent
generation technologies. Capacity, intermittent impacts
7. Transmission
planners should use explicit methods and assumptions behind methods for
evaluating all resources including demand side and intermittent generation
technologies and work with stakeholders to identify ways to standardize
methods across various studies so they can be compared.
8. Transmission plans
should fully integrate planning for reliability with planning for
competitive markets. ( put in introduction: planning processes should
facilitate market-driver enhancements to relieve congestion and provide
reasonable level of reliability.
9.
Transmission planning process should be publicly accountable.
10.
The transmission planning entity should have authority and responsibility
to implement the plan. |